1. Certainly a start and you did indeed write TCB at the uni-directional fringes with the adjacent signalboxes. I'd however have made a reference to the need for approaching train indications to the other boxes having passed the last protecting signal and vice versa, also the provision of Train Describer and Emergency Alarm as well as direct phone line from box-to-box.
Given the bi-directional single line portion over the viaduct, enhanced route locking and perhaps a direction switch should have been provided. Ditto the bi-directional Down Branch to C.
The main interface is with the Stone Terminal which could potentially have been designed to be operated from a separate local panel or directly by a shunter and it was this that would need description. However as you have drawn it, I read the design as still being controlled from the same signaller and track circuiting being provided, albeit with many of the moves being permissive and this information could have been shown on route boxes but even so some statement re the limits of TCB should have been made.
2. Given your choice of the Stone Terminal being controlled by the main signaller, then there is probably little to write re method of working between B and C. Instead though you should have said how the signaller would know that it was appropriate to clear 309 so that as the train is pulled into the headshunt that the terminal is ready to discharge the stone into the wagons as they pass underneath. Also how does the local operator get in contact with the driver if needs to stop in an emergency / adjust speed etc to avoid either the train only being half filled or alternatively all the stone spilling everywhere if things go wrong!
The signaller also needs to know that it is safe to clear 310 so that the driver can push back the now filled wagons through the stone bunker again (we don't want to trap any workers who may have needed to enter the area) and again when clearing 309 having disconnected the wagons ready for the run-round move.
Actually the control of movements in such an are are better done by a local operator who can actually concentrate on the activity, physically see what is happening and be in local radio contact with the train driver, rather than a remote signaller who has the rest of the railway under their control to worry about and could therefore be distracted.
Hence my supposition that what you have numbered 305, 307, 309, 310 and points 414 and 417 would be under the control of the Stone Bunker operator and so in a completely separate number sequence prefixed C.
Then there is a matter of "slotting" between the main signaller and this operator.
Operator at C would need to give a "slot" (i.e. an electrical control output into the main signaller's interlocking) as a pre-condition for them being able to set the oute(s) from their 151 up to the signal protecting the stone bunker - let's call it C9.
Alternatively you could have selected the boundary of the respective areas slightly different with the local operator only worrying about 307/309/310/411 and therefore the actual slots needed would be different to reflect this split. The key is that when one signal needs at least some element of control from a second operator that the ownership is allocated to one and the other is given a slot on that element which concerns them.
The operator at C would need an approaching train indication
"DB occ or DC occ w 415R" and the main signaller would need to have C's track indication CDG both to see the totality of 101's route but also to see a train on the berth of their 162.
The would need to be a direct phone between the main signaller and the operator at C and some consideration of whether any Train Description needed etc.
3. Probably not much to write. I think the key is that it should have been possible to have brought a train up to the protecting signal in EITHER direction when the viaduct in use in the opposite direction- which in your case the placement of 11 did not allow. Provision of a direction switch would have enabled the security of route locking to establish reservation in either of the Up or the Down directions in the vent that there was a need to use in degraded mode at a time when normal route setting and signal clearance not possible.
(29-08-2014, 05:18 PM)asrisaku Wrote: Dear PJW
I wish to try answering method of working. It would be good to get feedbacks more.
1. The method of block working on the main lines and branch lines should be shown, together with any interface arrangements.
Main lines and branch lines use track circuit block (TCB)
Is it good enough?
2. The method of working between the stone terminal and station B should be shown.
Freight trains from station B to Stone terminal C via down branch
-loco and wagon parks at stone terminal
-loco will go to headshunt and go to Run Round and go to Cripple Siding and go back to Stone Terminal
-loco and wagon leave stone terminal by using signal 162 to down Goods Loop via down branch(Back to station B)
3. The method of working over the single line viaduct at E should be shown.
-Any freight or passenger train from Down Main park at 111(Standage 400m is proposed).
-A train from UP Main can run to station B via viaduct while the other train from Down Main stands still.
-Once the train from UP Main clear viaduct E(Last Track CN clear) the train from Down can go to section 'F'
_____________________________________________
Could you please explain a bit about slot control on 151, 309, 310 at Stone bunker? I am totally blank this topic?
Best regards, Arnut